Ramadan
Ramadan Order Calendar: Backward Deadline for Dates
The order deadline is calculated backwards: expected start of Ramadan, minus shelf delivery, customs clearance, transit, preparation and departure, then production and inspection. Every duration is a working assumption that you change in the tool yourself, never a guaranteed lead time or a market average.
Editable assumptions
…
Indicative calculation: it does not replace a dated quotation or your forwarder's information.
What is this calendar for?
Ramadan moves forward by about 11 days every year, while the harvest stays in October to December. From one season to the next, the window for ordering, producing and shipping does not move at the same pace as your habits. The calendar on this page turns a shelf date into an order deadline, using durations that you set yourself. This page explains the logic; the deadline tool covers how to use it.
How do you get from the shelf date back to the order date?
Start from the expected start of Ramadan, then subtract, step by step, the time each link in the chain takes:
Order deadline = expected start of Ramadan, minus shelf delivery, minus customs clearance, minus transit, minus preparation and departure, minus production and inspection.
| Item | What it covers | Who knows the duration |
|---|---|---|
| Shelf delivery | Delivery to warehouse, repacking if needed, distribution to stores | You, your distributor |
| Customs clearance | Declaration, inspections, payment of duties and VAT, release | Your forwarder or customs broker |
| Transit | Sea voyage, possible transshipment, waiting time at port | Carrier, forwarder |
| Preparation and departure | Loading, export formalities, delivery to port, vessel cut-off | Exporter |
| Production and inspection | Sorting, grading, packing, disinfestation, export inspections | Exporter, supplier |
The Incoterm you choose moves responsibility for some items: under FOB, transit is yours, whereas under CIF the seller books it. The calculation is the same, but the person you need to ask changes.
A reasoned example: shelf-ready for Ramadan 2027
Take the expected start of Ramadan, around 8 February 2027. The durations below are working assumptions for demonstration: they describe neither a Tamra Export lead time nor a market average, and you will replace them with those of your forwarder and your supplier.
| Item | Demonstration assumption |
|---|---|
| Shelf delivery | 14 days |
| Customs clearance | 7 days |
| Transit | 14 days |
| Preparation and departure | 7 days |
| Production and inspection | 21 days |
| Total | 63 days |
Counting back 63 days from 8 February 2027 gives 7 December 2026. Two variations show how sensitive the result is. If transit grows by 14 days (a more distant destination, a transshipment), the deadline moves to 23 November 2026. If the crescent is sighted a day earlier, everything moves back a day. On 13 November 2026, the first assumption leaves 24 days of margin and the second 10: the same order is "open" in one case and "tight" in the other. With a longer chain, the date would already have passed.
How should you read the date you get?
A distant deadline does not mean volumes are available: it only says the calendar allows it. To reserve lots you need a quotation and then a written agreement. A near deadline signals that there is no margin for a production delay, a full vessel or an inspection on arrival. A deadline already passed forces a choice: a simpler format, a smaller first shipment, or a move to the next Ramadan.
What are the limits of the calculation?
The calculation adds the durations one after the other. In practice some steps overlap: part of a lot may be produced while another part waits for its inspections. A sequential calculation is therefore prudent, but it ignores port congestion, public holidays and reefer container availability. The start date of Ramadan remains an estimate, within a day either way. To size the load, also use the container load simulator; for export formalities, see the page on disinfestation and phytosanitary rules.
Frequently asked questions
How is the order deadline calculated?
Start from the expected start of Ramadan and subtract, in reverse order of the chain, shelf delivery, customs clearance, transit, preparation and departure, then production and inspection. The result is the date by which the order must be placed. It is worth exactly as much as the durations you enter.
What does the calculation take into account (production, freight, customs)?
Five items: shelf delivery, customs clearance, transit, preparation and departure, and production and inspection. Freight corresponds to transit, customs to clearance. Neither prices nor duties are calculated here; for the full cost, see the export cost calculator. Samples, negotiation and packaging approval take place before the order date and are not counted.
Is the Ramadan date certain or estimated?
Estimated. Ramadan 2027 is expected to start around 8 February 2027, within a day either way depending on the sighting of the crescent; Eid al-Fitr around 9-10 March 2027. Ramadan 2028 is expected around 28 January 2028. These dates come from an astronomical calculation, not from an official announcement.
Does the calculation change with my destination country?
Yes, through the durations you enter: transit and customs clearance vary from one country and port to another, and so do distribution times. The tool lets you choose a destination zone, but its starting values are working assumptions that you should confirm with your forwarder.
What if this year's order window has already closed?
Several options remain: simplify the format, reduce the first shipment, accept shelves stocked later in the month, or aim at the following Ramadan by starting preparation at harvest. Air freight exists, but it weighs heavily on a bulky product; price it before choosing it.
Can I receive this calendar by email?
The site lets you ask for the result by email from the page. In any case, you can attach your deadline and your assumptions to a quotation request: that lets us check together whether the calendar holds, item by item.
Is the tool updated every year?
The Ramadan start dates are estimates that need revisiting each year, and you can change them in the tool at any time. The default durations are working assumptions, not updated data: it is up to you to check them against your forwarder's figures.
Does the calculation take the transport mode into account (reefer or not)?
Not directly: the tool reasons in days per step. The transport mode mainly affects transit and preparation, for example the availability of a reefer container. Enter the durations your forwarder confirms for the mode you chose. Cold storage at 0 to 4 °C remains recommended for dates.
Can I request a quotation directly from the tool?
Yes. You can request a quotation stating your deadline, your destination and your duration assumptions. The reply is a dated quotation within 24 to 48 hours, which sets out what the exporter confirms, quantities and schedule included, before any commitment.
Where does the data used in the calculation come from?
The Ramadan start dates come from a standard astronomical calculation, with a one-day uncertainty. The durations per step are working assumptions: they rest on no published average. For reliable figures, rely on your forwarder, your customs broker and your supplier.
Should I add a safety margin?
Yes, and the simplest approach is to build it into each duration rather than adding it at the end. The crescent can shift the date by a day, a vessel can be full, an inspection can take longer. A margin makes the deadline less precise but more realistic.